Meltshop (400,000 ton/yr)
• EAF: 50 Tons
• LF: 50 tons
• CCM: two 3 strand machines
Bar mill (300,000, ton/yr)
• Reheating Furnace: 2*30 Tons/Hr walking hearth type
• 3 High Rougher
• Intermediate terrain
• Finishing Line: 2
• Cooling beds: 2
Wire Rod Mill (400,000 ton/yr)
• Reheating Furnace: 60 Tons/hr walking hearth type
• Roughing section
• Intermediate Section
• Monoblock: 75 M/s for 5.5 mm
Section Mill (500,000 ton/yr)
• Reheating Furnace: 75 Tons/ Hr pusher type with radiant
burners
• Roughing section: Blooming mill
• Intermediate and Finishing: Universal stands + Edger
• Cooling Bed: 66 Meters
Production Process:
|